TCE
secures contract for nuclear power project
November
28, 2000
TCE
Consulting Engineers Limited(TCE) has secured
the contract to render consultancy services for
the preparation of detailed project report and
detailed pre-construction phase design works for
the prestigious 500 Mwe Prototype Fast Breeder
Reactor (PFBR) project the Indira Gandhi Centre
for Atomic Research (IGCAR). The contract between
TCE and IGCAR was signed in Bangalore on November
14, 2000.
The
project is proposed to be set up at Kalpakkam,
Tamil Nadu. The work will be carried out in 2
phases. The first phase will cover the preliminary
design and engineering works including plant layout,
preparation of bill of materials and cost estimates,
while basic and detailed designs and preparation
of specifications for materials, equipment and
buildings will be undertaken during the second
phase.
Work
on the assignment will start immediately and is
scheduled to be completed by June 2002.
|
|