Tata
Projects introduces new methodology for steam generator drum
erection in India
August 18, 2004
Tata
Projects have successfully lifted 500 MW steam
generator drum of Unit-IX at NTPC's Vindyachal
Super Thermal Power Plant on August 18, 2004 using
'Hydraulic Strand Jacking' method.
It is for the first time that any Indian erection
contractor has used this technique and therefore
it evoked considerable interest from our
clients, NTPC / BHEL and other contractors.
Two
hydraulic jacks of 180 tons capacity each along
with a set of strands, both specially transported
from UK , operating from a height of 90 meters
were utilised to hoist the steam generator drum
weighing approximately 240 tons to a height of
76 meters in a matter of 10 hours. In India, conventionally,
steam generator drums are being lifted by using
15 ton winches with multi-sheave pulleys requiring
considerable pre and post preparation time and
auxiliary source of power.
The
new system adopted, in addition to being fully
‘fail-safe’, is most unobtrusive and allows other
works to continue unhindered prior to and after
the lifting operation, thus providing about two
weeks savings in time schedule. Going by the enthusiasm
the new erection method has generated, it is expected
that this process will be widely adopted in other
projects, with likelihood of its becoming a standard
erection practice in future.
On
this special occasion it is worth remembering
that Tata Projects was associated with the erection
of India’s first 500MW indigenous steam generator
Unit-VI for Tata Power’s Trombay Plant in 1988.
There after the company created a national record
in erecting the 500 MW steam generator drum of
Unit-VI at NTPC's Talcher Super Thermal Power
Plant in 110 days during April 2002. This was
followed by the highest tonnage and pressure part
joints erected on any project in India in a month
at Unit-III NTPC's Rihand Super Thermal Power
Plant in November 2003.
|
|