We
can’t leave an asset as large as Dabhol stranded
Economic
Times - March 29, 2002
Since
1910, Tata Power has been generating electricity
and now claims to be the largest independent power
producer in India. It is also one of the bidders
for the troubled Dabhol Power company, promoted
by Enron Corp. In contrast to other investors
who are stampeding to leave India’s power sector,
Tata Power actually makes money generating, transmitting
and distributing electricity -- a healthy 11.6
per cent margin on sales of Rs 3,361 crore last
year.
Adi Engineer, managing director, Tata Power,
spoke to ET’s Abheek Barman and Soma Banerjee
about the company’s plans and the rationale behind
the Enron bid. Excerpts from the interview:
Does Enron Corp,
which is bankrupt, have the right to push for
a selling price for DPC or do these claims lie
solely with lenders to the project who have first
charge?
We’ve signed a confidentiality agreement and so
we can’t talk about a lot of issues pertaining
to negotiations. But as far as DPC is concerned
Tata Power sees it as an opportunity. Today, we’re
the largest private power company in India: our
capacity of 2,300 MW is higher even than DPC’s
2,100 MW. We have no conflict with Dabhol as such
because they are generators of power and we are
an integrated power company. That’s why we’re
interested in DPC.
DPC is more or less ready for operations. It’s
in Maharashtra, where we do a lot of business,
it’s a very good asset and it’s for sale. But
ultimately, DPC’s feasibility will depend on the
quality of the contracts it is based on. The prevailing
ones weren’t good, we thought so initially and
our hunch has been borne out. DPC didn’t get bogged
down on technical issues, it was done in because
of the way the contracts were structured. Therefore
we want to see the contracts set right, we want
to correct the problem at the origin and to do
that we have to redo the contracts. Ultimately,
you have to ask: is this affordable for people?
If yes, the project works.
What contracts need to be reworked? The PPA
with MSEB...
Yes, that’s one of the contracts that needs to
be changed. The original PPA won’t work. We need
a new PPA which has a two-part tariff -- something
like what other IPPs are working on. DPC’s tariff
has to be benchmarked with that of similar projects.
Then, there are other contracts on which the PPA
is based, for gas purchase and operation and maintenance.
These too have to be reworked. At the end of it,
the gas purchase contract, the O&M contract
have to all add to a price to make the power affordable.
If Tata Power could help in doing that then we
would be quite happy to take up the project. But
do you think this is really doable because a large
part of the work has already been completed and
this has been done based on certain assured conditions.
Say, for instance, the O&M operator may not
agree to the new terms or the gas supplier may
not like to continue supplies on reworked conditions...
The crux lies therefore in renegotiating these
contracts. Either these guys come round to a price
that is more competitive or we invite fresh bids
and we sign new contracts. We can’t leave an asset
as large as Dabhol stranded.
So you’re open to calling fresh contracts?
Exactly. However, its quite possible that the
existing contractors are willing to review existing
positions and decide that it’s worth renegotiating.
Ultimately, there’s no point if everybody takes
a hard and fast position: that way it just becomes
a legal dispute where you go to court and hope
you win, but finally, what do you do with just
a court decree? What everybody wants is a running
project and power that consumers can afford. The
project has to run at a benchmarked price.
Today, everybody is talking of a cut, aren’t they?
Everybody realises that there has to be a cut
to make the power affordable. The capital cost
of the project cannot support this tariff, it
should be lower. Otherwise, you simply have a
costly project that is not generating power because
nobody’s willing to buy it.
But isn’t the capital cost very high?
We have not done the due diligence of the project
yet and so we do not have definite answers on
that. But from the published figures you can see
that there’s a substantial difference between
comparable components of DPC and other projects.
For example, the DPC liquid natural gas terminals
are considerably dearer than what has been bid
for a similar terminal at Dahej.
Who is doing all the negotiations with potential
buyers like you? The lenders? The equity holders?
MSEB?
MSEB is one of the equity holders of Dabhol. MSEB
is also the buyer of DPC power so they’re on both
sides. The gas contracts are often signed bilaterally
between governments. Then there are a large number
of lenders. So, there are a number of entities
on the seller’s side which have to first come
to an arrangement among themselves. The project
is already in distress, debt has to be restructured
because the rates of interest that have been contracted
earlier -- 16 to 21 per cent --- are very high
compared to prevailing rates.
So times have changed and we have to restructure
the project accordingly. If somebody can do it,
it has to be a seasoned power player and a seasoned
gas player. Its not as if DPC can be broken up
into two separate gas and electricity projects.
It’s a highly integrated plant. Remember, of the
3 million tonnes of gas that the terminal can
handle, 2.1 million tonne will be required for
the power plant.
Are you tying up with GAIL to form a consortium
to bid for DPC?
We have a good relationship with GAIL because
it supplies gas to Trombay and we’ve worked together
on some other possibilities. But unless there’s
some more clarity on the future of DPC, it’s too
early to comment on a consortium. We haven’t tied
up formally. Of course, there’s a synergy: GAIL
is India’s biggest gas distributor and we’re in
the power business. And DPC is essentially a gas-in
power-out project.
Have you decided how you will bid?
Actually, well before that the lenders and equity
holders have to work out a lot of things. For
instance, they have to decide on the structure
of the project, rework contracts, get a reasonable
business plan with possible tariff structures
in place and then call for bids. There’s no hurry.
The Dabhol project isn’t running but it’s not
that all of Maharashtra is getting blacked out.
What little shortage Maharashtra faces at peak
hours, it buys from other states. We sell power
to MSEB at Rs 2.50 per unit whereas MSEB bought
power from DPC at Rs 5 to Rs 7 per unit. So there’s
quite a bit of rationalisation to be done and
the sellers have to work out most of this.
How do you justify bidding for a large project
like DPC when almost every state electricity board
is bankrupt?
Well, DPC is there on the ground and if all the
contracts are renegotiated so as to make the tariffs
affordable, then it is a good buy.
But will SEBs suddenly turn around and start
paying up?
That is an altogether a different matter. The
answer lies in an integrated approach where a
generator takes up distribution and has full powers
to collect the dues from consumers. It’s like
the business model I operate on in Mumbai. I give
power from the plant to the doorstep and if the
consumer doesn’t pay, I cut him off. The future
lies in developing integrated projects with generation,
transmission and distribution rights with the
same company.

|
|